Electric smoke ventilator has function of lighting and ventilation, which is an indispensable facility for lighting and ventilation of enterprise factories. To give full play to the functions of electric smoke vent, scientific installation is indispensable. Mcwell will share five key points of installing smoke vents.

 1. Installation steps of electric smoke ventilator:

(1) Elevation positioning; (2) Hole treatment; (3) Installing embedded parts; (4) Checking the condition of the smoke vent skylights; (5) Installing the skylight; (6) Debugging; (7) Cleaning up the site.

2. The smoke vent rooflight window hole needs to be scientifically designed:

the size of the window hole must conform to the drawing design. When installing roof vents, the position and height control line must be placed according to the drawing size, and the height of the hole must meet the drawing design requirements.

3. Installation inspection of smoke vents:

inspection is an important step in installation. After the skylight is transported to the construction site, start installation according to the design diagram. First, check whether the transit system of the skylight is installed firmly, and then install the smoke ventilation after the inspection is qualified.

4. Debugging of smoke vent:

After installation according to the drawings, the operation of the skylight needs to be tested. If there is any malfunction, you should find out the reason and make adjustments immediately.

5. Electric lighting and smoke exhaust skylight inspection:

After debugging, the sealing treatment of the skylight gap and the anti-corrosion treatment of the fixed parts are scientific and reasonable, and meet the relevant technical specifications.
 